go to top scroll for more

Projects


Projects: Projects for Investigator
Reference Number NIA_SGN0048
Title Bar Hole Zone Rating (Stage 1)
Status Completed
Energy Categories Fossil Fuels: Oil Gas and Coal(Oil and Gas, Refining, transport and storage of oil and gas) 100%;
Research Types Applied Research and Development 100%
Science and Technology Fields ENGINEERING AND TECHNOLOGY (Mechanical, Aeronautical and Manufacturing Engineering) 100%
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
SGN
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 February 2015
End Date 31 August 2015
Duration 7 months
Total Grant Value £11,716
Industrial Sectors Manufacturing
Region South East
Programme Emergency
 
Investigators Principal Investigator Project Contact , SGN (100.000%)
Web Site http://www.smarternetworks.org/Project/NIA_SGN0048
Objectives

The objectives of this project is to produce a report detailing a risk assessment for the bar holing activity and the suitability of any powered device to locate and detect gas escapes. The following will be considered within the technical report:
  • Assess the likely environment in which the bar hole sampling tool will be used with respect to explosive risk.
  • Review the relevant legislation requirements for working in such environments.
  • Review the potential implications within the tool design such as battery or air powered tools.
  • Identify under what circumstances the battery drill should be prohibited. Such as on medium pressure escapes, where gas can be heard or felt.
  • Identify what control measures need to be incorporated into the design of the device and what standards they should comply to.
  • Identify any operational control measures which need to be applied to the use of the device.
  • Identify if any qualification testing is required to demonstrate product safety in explosive environments.
  • Discuss/establish technical requirements for the design with a potential manufacturer.
Expected Benefits:

The success criteria of this project will be determined against the quality and content of the technical assessment. The project will be deemed to be successful if the following outcomes are achieved:
  • Delivery of a report detailing the risk assessment for the activity of bar holing and the design requirements for a powered bar holing tool covering all key areas as detailed in the objectives.
  • Provide relevant conclusions on the technical requirements that can be used to support a manufacturer in the design and development of a new powered bar holing tool.
  • The conclusions of this project will support a future Stage 2 project which will look to work with a manufacturer to design a tool that is compliant with the recommendations made in Stage 1.
Abstract The scope of the project is to carry out a detailed technical, environmental and legislative assessment on the bar hole sampling tools used in the GB gas industry to date and identify the control measures and technical design requirements that can be discussed with a manufacturer in a future Stage 2.
Publications (none)
Final Report (none)
Added to Database 07/10/16